Instead of repeating technical parameters and role division, the four stages of "selection-quotation-installation-acceptance" are strung together into a project process chain with handover standards, card-point cracking and time nodes.
The most common occurrence of splicing screen projects is not "can't do it", but "stuck between stages".The plan was fixed and the quotation was submitted for three rounds, but the quotation subjects of the three companies were different, and Party A could not compare the prices. When the equipment arrived, the engineer found that the wall did not bear enough weight. The plan had to be changed, the construction period had to be extended and the cost had to be discussed again. After the system was installed, Party A said that "the conditions for use have not been met". After the acceptance was delayed for three months, the payment, the payment from the integrator and the payment was suspended.These problems are not that a certain stage is not well done, but that there is no "handover stick" between stages-the output of the previous stage has not become the input of the next stage, the conditions for entering the next stage are not clearly written, and they are stuck. I don't know who to look for and on what basis to break the game.This article does not repeat how to choose technical parameters, how to divide the roles of the three parties, and how to give those contents to the corresponding special articles. This article only does one thing: string the four stages into oneHandover standards, process card points, time nodes and dispute resolution mechanismsThe project process chain, so that the project from demand to delivery really go through, go.
1. first look at a timeline: four stages, five milestones and three handover stages.
The value of the project process article is not in "what to do at each stage", but in "when to do what and to what extent to enter the next stage". The following timeline shows the four stages and key milestones.
- Milestone: Requirement Confirmation (Starting Point of Selection Phase)
- Milestone 2: double confirmation of scheme and site conditions (type selection → handover of quotation)
- Milestone 3: quotation and contract scope lock (quotation → handover of installation)
- Milestone 4: installation and commissioning are completed, and the preliminary inspection is passed (handover of installation → acceptance)
- Milestone 5: Final Inspection Passing and Quality Assurance Starting Calculation (Project Cogging)
2. selection stage: not "select equipment", but "lock input conditions"
The most common mistake in the selection stage is to compare parameters, brands and prices as soon as they come up. The correct order is to lock the "input conditions" of the project first, and then let the technical parameters match the conditions. Whether the stitching is 3.5 or 1.8, the size is 55 or 65, and the resolution is 1080P or 4K, all depend on the same set of inputs:Scene, closest viewing distance, available wall dimensions, source list, runtime, budget boundary.The input conditions are not clear, and the parameters are idling.
Judgment sequence of type selection stage
Parameter selection has a sequential dependency and cannot be tiled at the same time. One available order is:
- Set the scene and viewing distance first.Surveillance, showrooms, conference rooms, retail, what is the nearest viewing distance-this determines the lower limit of single-screen size and patchwork level.
- Re-measure the available wall dimensions.After deducting the maintenance space, cabinet height and wrapping edge, several columns and rows can be placed-this determines the number of splicing columns and the feasible range of single screen size.
- Then make a list of sources.The number of cameras, computers, playback boxes, and conference terminals, and the native resolution-this determines the specifications and number of processors, matrices, and decoders.
- Re-confirm the run time and environmental conditions.Whether it is 7 × 24, how much ambient illuminance, and whether there is dust vibration-this determines the panel level (industrial or commercial) and brightness level.
- Finally, make a choice with the budget.In the scheme that meets the first four items, the flat-splice grade, panel source and accessory grade shall be selected according to the budget.
The key to this sequence is:The front judgment is the back constraint. Set the viewing distance before you know whether the seam should go to 0.88mm. First measure the wall surface before you know whether the 55-inch three columns will be too wide. The signal source is listed first before we know whether the processor needs multiple 4K inputs. Skip the front directly than the price, and often end up pushing back and coming back.
Two core documents for the selection phase
Requirements Definition TableTo be completed by Party A and verified by the integrator and the engineering contractor. The core fields include application scenario, nearest viewing distance, available wall size, signal source list (type x quantity x native resolution), whether to run 7 x 24, acceptance core indicators, budget range, and later expansion plan. This table is the "constitution" of the project, and it shall prevail for subsequent plans, quotations and acceptance.The fields that Party A cannot fill in are the fields that need to be confirmed on site by the three parties before the scheme stage, instead of "discovering" them at the construction stage ".
Site Condition Investigation Table: completed by the engineer and signed by the integrator for confirmation. The core content includes wall type and load-bearing accounting, power capacity and socket location, network access conditions, heat dissipation and maintenance space, construction channels and operating conditions.Site investigation must be completed in the selection and scheme stage and cannot be delayed to the installation stage. If the investigation is not carried out until the equipment is placed and the plan is decided to die, and it is found that the wall is not sufficiently load-bearing or maintenance space is insufficient, it will be reworked or changed, and the cost and construction period loss will be borne by the project.
After seeing the scheme in the selection stage, Party A wants to change the scene, position and signal source, resulting in repeated modification of the scheme. The cracking method is not to "urge Party A to make a decision as soon as possible", but to specify the "demand freeze date" on the demand definition form-it can be modified before this date, and then modify the change process and evaluate the impact of construction period and cost. Without a freeze-day project, the plan will never be finalized.
3. quotation stage: not "than the total price", but "than the three comparability"
The cards in the quote phase are very concentrated:The price difference reported by the three companies is 30%. Party A does not see where to travel. Integrators feel that the price has been reduced and engineers are worried that the construction scope will be reduced. The root cause is that the subject composition of the quotation is inconsistent-some include processors without cables, some include installation without debugging, some use A panel for screen body and some use A level. Only than the total price, equal to than three "account is not the same" bill.
split the quotation into three paragraphs and align them item by item
A comparable quotation for splicing screen shall be split into at least three paragraphs:Equipment and boards, integration and construction, service and delivery. After the three sections are separated, Party A can see in which section the low price is saved-whether the equipment uses low-grade panels, the scope of integrated construction shrinks, or the service delivery is compressed into "only communication number but not plan".
| Quotation paragraph | Accounts that must be aligned item by item | Common "incomparable" traps |
|---|---|---|
| Equipment and board | Specific screen model, panel source and grade (A /A), patchwork specification, brightness and resolution; Processor model, number of input/output channels, processing capacity under multi-channel high-resolution input; Matrix/decoder model and number of channels; Bracket type (wall hanging/front maintenance hydraulic/floor cabinet) | Only write "55-inch splicing screen" and do not write model and panel grade; The processor only writes "support 4K" and does not write continuous processing capability under multi-channel 4K. The bracket only writes "standard" and does not write load-bearing and maintenance methods. |
| Integration and Construction | Cable brand and specification (HDMI version/optical fiber/network cable), cable length and laying method; Cabinet/distribution frame; Screen installation and leveling; Wall reinforcement (if any); Removal of old equipment; Decoration restoration | Cable quotation according to "item" does not include length and specification; installation fee "one price" but does not include aerial work/night construction/wall reinforcement; old screen removal and decoration restoration are listed as "later additions" |
| Service and Delivery | Commissioning scope (whether it is "communication number" or "color calibration of plan"); training sessions and objects; warranty period and starting point; after-sales response time limit; spare parts supply commitment | Verbal promise "including debugging", but the contract did not write plan preparation and multiple rounds of revision; Training only writes "provide training" instead of sessions and materials; The starting point of quality assurance is "delivery date" instead of "acceptance date" |
Operational actions of Party A's horizontal price comparison
All bidders are required to submit their quotations using the same itemized pricing template, rather than accepting quotation forms with varying formats. Focus on checking four types of "incomparable items": whether the screen body indicates the specific model and panel grade; Whether the processor indicates the continuous processing capacity under the target number of input channels and the number of windows opened; Whether the brand, version and length of the cable are specified; Whether the installation fee covers wall reinforcement, high-altitude operation and demolition of old equipment.Any item that says "standard", "actual" and "another discussion" should be clarified in writing at the bid evaluation stage, not after the contract is signed.
"Ultra-low price" quotations are often used to recover profits in the later period in three ways: first, equipment degradation (panel from A to A or assembly screen); The second is the construction additions (wall reinforcement, power supply renovation and cable redrawing are said to be "accidental discovery"); Third, the service shrinks (debugging only involves communication numbers, and additional charges for plans and training). When comparing prices, Party A shall require the bidder to make a written explanation of "which costs have been included and which may be additionally incurred", and shall make the explanation as an annex to the contract.
Five types of clauses that must be locked in a contract
The end of the offer is the contract, and the contract is the only basis for adjudication when a dispute occurs. The following five categories of clauses should be confirmed one by one before signing the contract, instead of copying the template:ACCEPTANCE CRITERIA CLAUSE(Quantify the value, do not write "meet the requirements");Duration and delay liability clause(Distinguish between equipment arrival delay and construction delay);Amendment Clause(The pricing method of expansion, location change and signal source change shall clarify the specific meaning of "expandable");Warranty Starting and Spare Parts Supply Terms(From the acceptance, specify the supply period of spare parts);Payment and Acceptance Linked Clause(specify the time limit for starting acceptance and the condition that "overdue acceptance is deemed to be passed").
Party A got three quotations in different formats, and did not know which one was reasonable, so it could only pick the one with the lowest total price. As a result, the number of items added in the later period continued. The solution isn’t to “just find a few more,” but ratherParty A or Integrator shall provide a unified itemized quotation template, requiring all bidders to fill in the same format., and write "any items not listed as included" into the bid evaluation requirements, eliminating the space of "winning the bid at a low price and adding items at a later stage" from the source.
4. installation stage: not "to the site to see", but "according to the confirmed conditions of construction"
The most common mistake in the installation stage is to put the scene investigation in this stage. If you wait until the equipment arrives and the engineer enters the site before you start to look at the wall load-bearing, power supply capacity and maintenance space, the plan has been fixed and the equipment has been ordered. If problems are found, you can only rework or change them.The correct positioning is: the installation stage is "according to the site conditions confirmed in the selection and scheme stage", not "to the site to start to confirm the conditions".
Three parallel lines in the installation phase
The installation phase is not a single action, but three lines are advanced in parallel. Any problem in one line will slow down the whole:
- Structure and installation line (engineering led)Wall reinforcement, bracket installation, screen fixing, leveling and sewing. The quality of this line directly determines the uniformity and surface flatness of the flat seam, and also determines whether the later maintenance is convenient.
- Signal and integration line (integrator-led): Cable laying, equipment connection, processor/matrix/decoder configuration, signal link segmentation test. The key to this line is "segmented testing"-signal source to processor, processor to screen, confirmed segment by segment, instead of debugging together after all.
- Commissioning Verification Line (Integrator and Engineer): display effect (brightness, stitching, color consistency), system function (screen projection, window opening, roaming, remote management), business process (whether real tasks can be completed). Debugging is not "power on to see whether it is bright or not", but check item by item according to the acceptance indicators in the demand definition table.
Three records that must be produced during the installation phase
Acceptance Sheet of Construction Records and Concealed Works: Record the wall reinforcement method, bracket installation position, cable laying path and power access point, which shall be filled in by the engineer and signed by the integrator and Party A's representative. Once the concealed works are sealed, it is difficult to trace back the problems in the later period, and the acceptance must be completed before the sealing plate.
Signal Link Segment Test Record: Test and record section by section according to "signal source → processor → cable → screen body", which shall be filled in by the integrator and signed by the engineer to confirm the cable construction quality. This record is the key basis for distinguishing between "equipment problems" and "construction problems", and is also the basis for initial and final inspection.
Commissioning Record and Rectification List: Record the display, function and process problems found during debugging, and specify the responsible party and rectification period. The commissioning record is not an "internal work log", but a necessary document to enter the acceptance stage.
Insufficient wall load-bearing, insufficient power supply capacity, incorrect network interface location, and occupied maintenance space-if these problems occur after the equipment arrives, it is rework and construction period delay. There are two ways to crack:First, the scene survey moved forward to the program stage., the survey form shall be filled in by the engineer and signed by the integrator for confirmation;Second, the contract stipulates that "the cost of reinforcement and renovation caused by the omission of the survey shall be borne by the responsible party of the survey"Let the survey is not a formality, but a formal action with responsibility and restraint.
5. acceptance stage: not "normal power", but "three-level acceptance dispute settlement mechanism"
The most common mistake in the acceptance stage is to regard "the picture is normal after power-on" as passing the acceptance. The real acceptance is three-level progressive:Arrival acceptance, installation acceptance, function and process acceptance. All three levels have passed before entering the final inspection and quality assurance calculation.
Contents of Level 3 Acceptance
Level 1: Acceptance on arrival. Check whether the packaging appearance, product model and quantity, serial number, accessories and project information are complete. This is the first pass of project risk, and many problems of equipment degradation and model discrepancies can be found when they arrive. Abnormalities must be recorded on the spot and confirmed by the supplier, and cannot be "signed for first".
Level 2: installation acceptance. Check the wall reinforcement, bracket fixing, screen body leveling and joint, power supply and cable construction, heat dissipation and maintenance space. The core of this level is "hidden engineering record" and "installation accuracy"-if the uniformity and surface flatness of the flat seam are not up to standard at this level, it will be difficult to make up for it through debugging.
Level 3: functional and process acceptance. Check the display effect (brightness, resolution, patchwork, color consistency), system function (screen projection, window opening, roaming, remote management), business process (whether it can complete the real task). This level must be based on the acceptance indicators in the Demand Definition Table, rather than judging "whether it looks good or not" based on subjective feelings ".
| Acceptance Level | Verification content | According to the document | Signatory |
|---|---|---|---|
| Arrival acceptance | Package appearance, model and quantity, serial number, accessories data and abnormal records | Arrival Acceptance List Equipment List and Configuration Table | Party A's representatives, integrators and suppliers |
| Installation acceptance | Wall reinforcement, bracket fixation, screen body leveling and seaming, power cable, heat dissipation and maintenance space | Construction Records and Concealed Works Acceptance Sheet Site Condition Investigation Sheet | Engineer, integrator and representative of Party A |
| Function and process acceptance | Display effects (patchwork, brightness uniformity, dead points, color), system functions, business processes | Acceptance indicators of Commissioning Record and Rectification List and Requirement Definition Table | Integrator, representative of Party A and user department |
What to do if the acceptance does not pass: the processing mechanism is more important than the acceptance criteria
The acceptance criteria are written in more detail. If the acceptance fails, there is no handling mechanism and the dispute cannot be resolved. The following four mechanisms shall be agreed in advance in the contract or acceptance plan.
First, the responsibility for rectification is determined: first qualitative, then responsibility. When the acceptance fails, the first step is not to blame, but to record the problem phenomenon in writing and identify it: whether it is the defect of the product itself (panel bad spot, uneven brightness), installation accuracy problem (uneven patching, flatness out of tolerance), signal link problem (resolution mismatch, black screen switching), or function failure (plan not configured, touch not calibrated). The qualitative basis is the quantitative criteria and test records in the contract. When the characterization is clear, the responsible party is naturally clear; skipping the characterization and direct accountability will only lead to a cycle of three parties holding different opinions.
Second, the rectification period and re-inspection time limit: set the time limit to avoid infinite cycle. The contract shall stipulate: how long will the responsible party complete the rectification after the acceptance fails? How long will Party A organize the re-inspection after the rectification is completed? If the re-inspection still fails, whether to continue the rectification, deduct the contract amount, or trigger the breach clause. The "rectification-re-inspection" cycle, which has no time limit, is a common reason for dragging out project refunds and deliveries.
The third is the payment processing during the rectification period: distinguish between the undisputed part and the disputed part. If the acceptance fails, it is reasonable that the acceptance payment will not be paid for the time being. However, the part that has passed the stage acceptance or the equipment payment unrelated to the disputed item shall not be frozen as a whole. The contract may stipulate that "the undisputed part shall be paid first, and the disputed part shall be paid after rectification and re-inspection", so as to avoid the stagnation of the whole payment due to local problems.
Fourth, the handling of Party A's delay in acceptance: written reminders are deemed to be approved clauses. If Party A delays the acceptance without justifiable reasons, the integrator and the engineer shall issue a written reminder and keep the delivery record. The clause in the contract stating that “failure to accept the work on time and failure to raise a written objection shall be deemed as acceptance” is the key to breaking the deadlock. Government projects should also address the requirements of acceptance audits by preparing comprehensive change records and test documentation in advance to avoid post-audit deductions.
Subjective standards such as "clear picture and even patchwork" make acceptance become Party A's discretion. Party A will not sign or say where it is unqualified, leaving the acceptance suspended indefinitely. The cracking method is to write the quantitative index into the contract (flat seam ≤ X mm, brightness uniformity ≥ X%, bad points ≤ X, surface flatness ± X mm), and agree on the acceptance start time limit, rectification time limit, re-inspection time limit and the "overdue as passed" clause.Acceptance is not driven by relationships, but by terms.
6. stage handover criteria: to what extent can we enter the next stage
Four stages is not a list of four juxtaposed, but a chain with a hand-over bar. Each handover requires clear "completion conditions" and "signature documents", otherwise the problems left over from the previous stage will be brought to the next stage, which will become more difficult to solve in the future.
| Handover | Completion Conditions | Handover Document | Signatory |
|---|---|---|---|
| Selection → Quotation | The requirement definition form is completed and frozen; the site condition survey form is completed and signed by both parties; the technical route and main equipment scope are confirmed. | Requirements Definition Table Site Condition Investigation Table Scheme and Equipment Scope Description | Representative of Party A, Project Manager of Integrator and Site Leader of Engineer |
| Quotation → Installation | Horizontal comparison of itemized quotations is completed; contract signing, scope and responsibilities are clearly written; equipment orders and construction schedule confirmation | Itemized Quotation, Contract and Annexes, Delivery Plan and Milestone Table | Party A's purchasing representative, integrator and engineer |
| Installation → Acceptance | Completion of construction records and acceptance of concealed works; passing of signal link segment test; closed loop of commissioning records and rectification list | Construction Record and Concealed Works Acceptance Sheet Signal Link Test Record Commissioning Record and Rectification List | Contractors, integrators, and the client’s on-site representatives |
| Acceptance → operation and maintenance | Level 3 acceptance passed; acceptance report signed; quality assurance starting; training and O & M handover completed | Acceptance Report, Quality Assurance and After-sales Commitment, Training Record and Operation Manual | Party A's project leader, integrator and engineer |
7. four types of project process differences: the same set of processes, different weights and risks.
The four-stage framework is applicable to all projects, but governments, enterprises, retail chains and transformation projects vary greatly in process rhythm, decision chain and risk focus. The same set of processes has different "stuck points" in different projects.
| Project type | Process rhythm characteristics | The easiest stage to get stuck | Specific risks |
|---|---|---|---|
| Government/Public Projects | Bidding parameters, bid evaluation methods, trust requirements, audit settlement; long decision-making chain, user and purchaser may be separated. | Selection stage (parameter preference) and acceptance stage (audit traceability) | The preference of parameters leads to the cancellation or challenge of the bid, the localization requirements of the letter are not met, and the changes and additions are retroactively deducted at the audit stage. |
| Corporate project | IT department, procurement department, use department tripartite game; budget approval chain determines project rhythm | Quoting phase (price reduction resulting in service shrinkage) and installation phase (compatibility with existing systems) | Frequent changes in user requirements; additional requirements for network and security by IT; reduced commissioning and training due to low bid prices |
| Retail Chain Project | Headquarters unified decision-making, multi-store replication; The store is only responsible for cooperating with the construction. | Installation phase (multi-store parallel organization and on-site adaptation) | Site conditions vary greatly from store to store, and standard solutions require site adaptation; headquarters and stores have different tolerances for downtime; spare parts matching for later single-store expansion |
| Renovation/Upgrade Project | Expansion or replacement on the basis of the original system; the user has the inertia to use the old system. | Selection phase (new and old compatible) and installation phase (short window construction) | Mismatch between interface and protocol due to missing data of old system; underestimation of removal and restoration cost; inconsistent color difference and brightness attenuation of old and new screens |
The core risks of government projects are "parameter compliance in the selection stage" and "audit traceability in the acceptance stage"; The core risks of enterprise projects are "service shrinkage caused by price reduction" and "compatibility with existing systems"; The core risks of retail chain are "organization and site adaptation of multi-store parallel construction"; The core risks of the renovation project are "the connection between the old and the new and the short window construction". The same process framework has a completely different risk focus, and additional confirmation and buffers should be reserved at the corresponding stage when the project starts.
8. common process errors
- Misunderstanding 1: Put the site investigation in the installation stage.Only when the equipment arrives and the engineer enters the site can the survey be conducted. The plan has been decided and the equipment has been ordered. If it is found that the load bearing is insufficient or the space is insufficient, it can only be reworked. The survey must be completed at the stage of type selection and scheme, and filled in by the engineer and signed by the integrator for confirmation.
- Myth 2: Think of the four stages as four side-by-side lists.There are no handover standards and signature documents between the stages, and the problems left over from the previous stage are brought to the next stage, which will become more difficult to solve. Each handover stage must have a “completion criteria and signature document.”
- Myth 3: The quotation is only more than the total price, not three paragraphs.The price difference between the three reports is 30%, but the subjects are different. The cheapest one is often added in the later period. It must be aligned item by item according to the three paragraphs "equipment and boards, integration and construction, service and delivery", and written clarification is required for items not listed.
- Myth 4: Acceptance criteria are written as subjective descriptions."Clear picture and even patchwork" cannot be used as the basis for acceptance. Quantitative indicators (patchwork ≤ X mm, brightness uniformity ≥ X%, bad spots ≤ X) can make acceptance based on evidence and rectification responsibility based on evidence.
- Misunderstanding 5: The contract only writes the total price and construction period, not the acceptance, change and warranty starting calculation.The contract is the only basis for adjudication in the event of a dispute. Acceptance criteria, duration delay liability, change pricing, quality assurance calculation, payment linkage five types of provisions, any kind of lack will become a deadlock in the dispute.
- Misunderstanding 6: If the acceptance is not passed, only accountability will be pursued, not qualitative first.Skip the "problem characterization" and directly pursue the responsibility. The three parties hold their own opinions. The dispute cannot be converged. The phenomenon is first recorded in writing and characterized by quantitative criteria, and the attribution of responsibility is naturally clear.
- Misunderstanding 7: There is no response mechanism for Party A to delay acceptance.There is no acceptance start-up time limit, rectification time limit, re-inspection time limit and "overdue as passed" clause, acceptance can be suspended indefinitely, collection and project closure are dragged to death.
9. FAQ
Of the four stages, which is the most problematic?
Not a certain stage itself, but the transition between stages. The handover from selection to quotation (whether the scheme and site conditions are double confirmed) and from installation to acceptance (whether the test record is signed by both parties) are the two nodes most likely to cause problems. The problem is not that the stage does not do well inside, but that "the output of the previous stage does not become the input of the next stage".
At which stage should the site investigation be placed?
Selection and scheme stage. The survey form shall be filled in by the engineer and signed by the integrator to confirm the wall load, power supply capacity, network conditions, maintenance space and construction channel. Putting the survey at the installation stage is tantamount to leaving the uncertainty of the program until the equipment arrives, with the highest rework and change costs. The contract shall stipulate that "the cost of reinforcement and renovation caused by the omission of the survey shall be borne by the responsible party of the survey".
The price difference between the three reports is 30%, how to judge which one is reasonable?
The quotation is split into "equipment and board, integration and construction, service and delivery" three paragraphs one by one alignment, rather than just the total price. Key verification points: Confirm that the display module model and panel grade match; verify that the processor’s processing capacity at the target channel count is clearly specified; ensure that cable brand, version, and length are listed; check whether the installation fee covers wall reinforcement, high-altitude work, and removal of old equipment; confirm that debugging includes contingency plans and color calibration; and verify that the warranty start date is tied to acceptance. For any item listed as “standard” or “to be negotiated,” a written clarification is required before comparing prices.
How to write the acceptance criteria to avoid disputes?
Write quantitative values, not subjective descriptions. Common calibers include: physical splicing ≤ 3.5mm (or according to 1.8/0.88mm); Brightness uniformity ≥ 90% (high requirement items ≥ 97%-98%); Unit damage ≤ 3; Surface flatness within 3mm; Flat seam uniformity ≥ 97%. At the same time, it is stated that "under what environmental conditions, with what test screen, by who jointly present the test". The more specific the standard, the less room for interpretation at the time of acceptance.
What if Party A delays acceptance?
It shall be stipulated in the contract that Party A shall organize the acceptance within X working days after receiving the application for acceptance. If the acceptance is not completed within the time limit and no written objection is raised, the acceptance shall be deemed to have passed. If Party A delays, the Integrator and the Engineer shall issue a written reminder and maintain a record of delivery. Government projects should also prepare a complete change record and test record in advance to deal with the audit phase of the retrospective. There is no "late as passed" clause, and acceptance can be suspended indefinitely.
What should be paid special attention to in the process of retail chain multi-store projects?
The core is "standardized replicable field adaptation". The headquarters has a unified configuration and installation method, but the site conditions (wall, power supply, network and maintenance space) of each store must be investigated and confirmed separately, and one template cannot be used to cover all stores. When multi-store parallel construction, it is necessary to specify the construction window period, downtime tolerance and person responsible for acceptance of each store, so as to avoid the situation that "the headquarters signs the contract and the stores do not cooperate.
10. Conclusion
The core of the splicing screen project process can be compressed into four sentences:
The site survey moves forward to the scheme stage; handover standards and signature documents are set up between stages; quotations are aligned item by item according to three paragraphs; acceptance and writing of quantitative criteria dispute handling mechanism.
The four stages are not four lists, but a chain with handover sticks, card points and breaking moves. The input conditions are locked in the selection stage, the scope and responsibilities are locked in the quotation stage, the construction is carried out according to the confirmed conditions in the installation stage, and the qualitative and dispute handling is carried out according to the quantitative criteria in the acceptance stage.At each handover pass, the signed and confirmed document is the basis for the next stage of dispute. At each card point, there should be a sentence "what action is stuck to break the game" instead of leaving it for temporary discussion when something goes wrong. The value of the process is not to keep the project out of problems, but to expose the problems at the right stage, to be solved by the right people, and to be accountable according to the right documents.
The stage is pushed forward by handover, and disputes are determined by documents. The process went through before the project was completed.